RLX completed key projects over the school holidays, with significant progress made across multiple sites. These projects are part of our continued commitment to improving educational and healthcare facilities, working efficiently within tight deadlines to ensure minimal disruption to our clients.

Leeds College Project: Enhancing Educational Spaces

One of our projects is underway in Leeds, where we are constructing an internal structural steel extension that will create additional teaching spaces. This project also includes the refurbishment of existing classrooms and the installation of glazed curtain walling, designed to bring natural light into the classrooms.

The external portion of the work was successfully completed over the summer holidays, ensuring that access for staff and students will not be compromised when they return for the new term. Internal works on the extension will continue during the school term, and we’re coordinating closely with the college to ensure minimal disruption.

In addition we have completed important fire safety upgrades in Lincoln and Newark which included:

  • Replacement of fire doors
  • Installation of new fire walls & glazing
  • Installation of new fire alarms
  • Fire barrier improvements
  • Ceiling and decoration works

 

We would like to extend a big thank you to our dedicated team and partners who made this progress possible within the tight deadlines.

Horatio’s Garden at Northern General Hospital, Sheffield: Progress Update

Our work on the Horatio’s Garden project at The Northern General Hospital in Sheffield has also progressed smoothly during this period. This garden, designed to provide therapeutic spaces for spinal injury patients is taking shape and works this month have included;

  • Formation of levels
  • Completion of external building foundations
  • Installation of underground services
  • Greenfix wall foundations
  • Stepoc retaining wall installation
  • RC walls for the garden room
  • Block work walls for outbuildings

What’s Next?

In the upcoming period, we will focus on the following key tasks:

  • Construction of the timber frame for the garden room
  • Cut and fill works to complete ground levels
  • Completion of brickwork
  • Installation of services in preparation for our landscaping team

 

As always, RLX Construction is proud to be part of projects that positively impact both the education and healthcare sectors, providing modern, functional, and welcoming spaces.

Share :

RLX News Feed

October 2024

Completion of Leeds College Refurbishment Project This month, RLX Construction successfully completed an extensive refurbishment

Read More

July 2024

RLX Construction kicked off a busy period of work across multiple academies in Lincoln, Leeds,

Read More

Let's Build Your Vision Together

Get in touch to discuss how we can bring your construction vision to life.