SHEFFIELD TEACHING HOSPITAL
DISTRICT NURSE BASE

totley 7.jpg

LOCATION

                   Sheffield 

DURATION

4 Weeks 

BRIEF

Nurse base 

Internal refurbishment 

PROJECT DESCRIPTION

Complete refurbishment of an existing commercial shop to create a office space for the district nurses. 

 

Works included demolition of existing finishes and partitions. Followed by installation of new partitions, complete re-wire including new fire and smoke detection to meet current regulations. New suspended ceiling, decorations, vinyl flooring, kitchen, bathroom ,UPVC frontage and composite door.   

 

Close liaison with department ensured the project was completed to meet the staffs specification.