BEIGHTON SCHOOL
INTERNAL & EXTERNAL REFURBISHMENT 

Beighton School 4.jpg

LOCATION

Sheffield

DURATION

6 weeks

BRIEF

Internal and External Refurbishments

PROJECT DESCRIPTION

The project consisted of the removal of a basement slab to the front elevation of the school, replacement of the perished steels and casting a new 250mm waterproof deck and access ramp with handrails.

A rear staircase was also added to bring access inline with current building regulations.

 

Internal works consisted of the removal of existing partition walls, damp proof works, then re-fit which included new walls, electrics, fire doors, decoration, suspended ceilings, decoration and floor coverings.